Item# Description Unit Quantity Unit Price Total
Paving Construction
1 Excavation(Roadway and Lots) C.Y. 4,233 7.50 31,748
2 6"Lime Stabilized Subgrade(6%by weight) S.Y. 8,976 3.25 29,172
3 6"Crushed Limestone Base S.Y. 6,926 8.25 57,140
4 2"HMAC Surface Course(including prime coat) S.Y. 6,926 9.40 65,104
5 Concrete Curb and Gutter(all types) L.F. 3,563 9.50 33,849
6 6"Reinforced Concrete Pavement S.Y. 332 36.00 11,952
7 4"Reinforced Concrete Sidewalk S.F. 8,906 3.00 26,718
8 Colored Sidewalk Ramps EACH 8 500.00 4,000
9 End/Road Markers EACH 6 250.00. 1,500
Paving Subtotal $261,182
Drainage System Construction
10 18"HDPE Pipe,(ADS,N-12 or approved equal w/water-
tight joints)Str.Backfill L.F. 317 37.00 11,729
11 24"HDPE Pipe,(ADS,N-12 or approved equal wwater-
/
tight joints)Str.Backfill L.F. 590 49.00 28,910
12 24"HDPE Pipe,(ADS,N-12 or approved equal w/water-
tight joints)Non-Str.Backfill L.F. 75 50.00 3,750
13 36"HDPE Pipe,(ADS,N-12 or approved equal w/water-
tight joints)Non-Str.Backfill L.F. 369 60.00 22,140
14 42"HDPE Pipe,(ADS,N-12 or approved equal w/water-
tight joints)Non-Str.Backfill L.F. 90 70.00 6,300
15 42"x45 deg.HDPE Bend EACH 1 250.00 250
16 4:1 Sloped End Treatment for 42"HDPE EACH 1 1,250.00 1,250
17 Standard 10'Recessed Inlet EACH 8 2,500.00 20,000
18 Standard Junction Box EACH 1 2,000.00 2,000
19 Rock Rip-Rap Channel Lining,on Filter Fabric S.Y. 26 50.00 1,290
Drainage System Subtotal $97,619
Water System Construction
20 6"PVC,C909 Cl 200,Water Line,Str.Backfill L.F. 217 20.00 4,340
21 6"PVC,C909 Cl 200,Water Line,Non-Str.Backfill L.F. 381 16.25 6,191
22 3"PVC,D2241 Cl 200 Water Line,Str.Backfill L.F. 190 17.00 3,230
23 3"PVC,ASTM D2241 CL 200 Water Line,Non-Str.Backfi1,J 543 10.00 5,430
24 Fire Hydrant Assembly EACH 2 2,650.00 5,300
25 Connect to Existing Waterline EACH 3 500.00 1,500
26 6"x13"M.J.Anchor Coupling EACH 1 130.00 130
27 6"x45 deg.Bend EACH 2 240.00 480
28 6"x3"Tapped Plug EACH 2 200.00 400
29 2"Blow Off Valve Assembly EACH 3 850.00 2,550
30 Water Service,1.5"type K Copper,short side(<20') EACH 5 650.00 3,250
31 Water Service, 1"type K Copper,short side(<20') EACH 3 450.00 1,350
32 Water Service,1.5"type K Copper,long side(>20') EACH 4 1,600.00 6,400
33 Water Service, 1.5"type K Copper,long side(>20') EACH 4 1,600.00 6,400
Water System Subtotal $46,951
1 of 2
PEBBLE CREEK,PHASE 9-F
MBESI PROJ#: 1065-0007
Engineer's Estimate of Construction Costs
March 5,2007
Item# Description Unit Quantity Unit Price Total
Sewer System Construction
34 6"PVC,D-3034 SDR 26 L.F. 1,162 7.50 8,715
35 6"PVC,D-2241 SDR 26 L.F. 20 7.50 150
36 Non-Str.Backfill(0'-5'Depth) L.F. 42 10.00 420
37 Str.Backfill(5'-8'Depth) L.F. 283 26.00 7,358
38 Str.Backfill(8'-10'Depth) L.F. 344 35.00 12,040
39 Non-Str.Backfill(5'-8'Depth) L.F. 222 12.00 2,664
40 Non-Str.Backfill(8'-10'Depth) L.F. 291 14.00 4,074
41 Standard Manhole,0-6 ft.deep EACH 8 2,500.00 20,000
42 Extra Depth for Manhole V.F. 33.4 250.00 8,345
43 Drop Connection EACH 2.0 750.00 1,500
44 Short Side 4"Sewer Service(<20') EACH 5 450.00 2,250
45 Long Side 4"Sewer Service(>20') EACH 13 1,400.00 18,200
46 Trench Safety(sewer) L.F. 1,182 1.00 1,182
Sewer System Subtotal $86,898
Erosion Control Construction
Erosion Control Plan&Sedimentation Control(per Item
106)(includes silt fencing,construction exits,straw bale
47 S.Y. 1 25,000.00 25,000
bathers,inlet protection,grass seeding,and any other
sedimentation control devices)
Erosion Control Subtotal $25,000
Total Construction Cost' $517,650
The above construction estimate is based on the engineer's preliminary opinion of probable construction costs. This
estimate constitutes our best judgment at this time. Please note that the engineer does not have any control over contractor
or supplier workloads and the degree to which inflation may affect project costs between now and the bid date. During
construction,additional features may become apparent as the work progresses,which will result in an increase in cost.
L• //q. � *�P ' ...','.. X4 *lt,
Jtery' .L. ,•beitson,P. . Date * • °� * �i
` JEFFERY L.ROBERTSON
4-o•
94745 i Q i
,rlO6• 4/CENSE •�::
2 of 2