HomeMy WebLinkAboutStaff Comments CITY OF COLLEGE STATION Planning d'Development Services 1101 Texas Avenue,P.O. Box 9960 College Station,Texas 77842 Phone 979.764.3570 /Fax 979.764.3496 MEMORANDUM July 23,2007 TO: Veronica Morgan,P.E.,Mitchell&Morgan,LLP,via v(a,mitchellandmorgan.com FROM: Jason Schubert,Staff Planner SUBJECT: SPRING CREEK COMMONS (PP) - Preliminary Plat Staff reviewed the above-mentioned Preliminary Plat as requested. The following page is a list of staff review comments detailing items that need to be addressed. If all comments have been addressed and the following information submitted by Monday,July 30,2007, 10:00 a.m.,your project will be placed on the next available Planning and Zoning Commission meeting scheduled for Thursday, August 16, 2007, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas Avenue. One(1) 24"x 36"copy of the revised Preliminary Plat;and Sixteen (16) 11"x 17"copies of the revised Preliminary Plat. If it is felt that all staff review comments will not be adequately addressed in the next review, please only submit the 24" x 36" revised copy. Upon receipt of the required documents for the Planning & Zoning meeting,your project will be considered formally filed with the City of College Station. Please note that if all comments have not been addressed, your project will be pulled from the scheduled Planning & Zoning Commission agenda. Your project may be placed on a future agenda once all the revisions have been made and the appropriate fees paid. Once your item has been scheduled for the P&Z meeting, the agenda and staff report can be accessed at the following web site on Monday the week of the P&Z meeting. http:// .cstx.gov/home/index.asp?page=2481. If you have any questions or need additional information,please call me at 979.764.3570. Attachments: Staff review comments cc: Frank Mihalopoulos,Corinth Properties,via frank@corinthprop.com Al Smith,St.Joseph Regional Health Center,via asmith@a,mail.st-joseph.org Penny Busch,Hammus Company,via pbusch@hammesco.com Case file#07-00500174 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans. Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 1 of 3 0 CITY OF COLLEGE STATION Planning d Development Services STAFF REVIEW COMMENTS NO. 1 Project: SPRING CREEK COMMONS (PP) -07-00500174 PLANNING 1. The boundaries of the plat do not close. Please revise. 2. Corridor Overlay district (OV) also exists on portions of the plat. Please label accordingly. 3. When final plats are submitted,all lots within a phase must be platted. As currently shown,Lots 4, 5,&6 are all part of Phase 4 and would need to be final platted together. If this is not your intent,please revise the Phase Plan while still ensuring each phase supports the infrastructure required by it. If phase boundaries change in the future,a revised preliminary plat must be submitted. 4. Note 5 states that Block 2,Lot 1 is not a buildable lot though the lot appears to require construction of a portion of Lakeway Drive, planting of the 50-foot vegetative buffer and provide underground storm water facilities along the eastern property boundary. This arrangement is not acceptable,please revise. 5. The Signage Plan may also be considered for revision. 6. The newly created Lot 2, Block 2 does not meet the minimum dimensions required with a C-1 zoning district. As per the October 11,2005 Parks Board minutes,it is our understanding that this area is to be donated to the City in connection with the adjacent park. Please revise. 7. Revise the note for the 30' access easement associated with Block 1, Lot 6 to state that the access easement will continue to Lakeway within Block 1,Lot 5. 8. It appears that the 30' access easement through the center of the plat has been removed. Please revise the plat to provide the easement,perhaps in a similar fashion as the aforementioned easement,but with a note stating that it will intersect Lakeway within Block 1,Lot 4. Reviewed by: Jason Schubert Date: July 23,2007 ENGINEERING COMMENTS NO. 1 1. Lakeway Drive is illustrated as a Major Collector on the city's thoroughfare plan which requires 80-ft Right-of-Way,please revise. 2. Please define PDE,as well as any other acronyms. 3. The proposed storm infrastructure is subject to change as the developments drainage report has not yet been submitted. 4. All proposed storm infrastructure which serves multiple lots has the option to be built to public standard and located within a public utility easement or located within a private utility easement. Any proposed Private Storm Infrastructure and corresponding Private Drainage Easements should be identified with ownership and maintenance responsibilities defined. 5. Please verify that all storm infrastructure has been properly identified as private or public, and the appropriate easement illustrated,and ownership and maintenance responsibilities designated. 6. It appears that some of the storm infrastructure has not been properly located within an easement and may meander in/out of public/private easements. 7. Please provide the required 20-ft PUE at the rear of all lots, these easements may be split between adjacent properties. 8. Our records indicate an existing 25-ft PUE located parallel to the property line adjacent to SH 6 (Volume 758,Page 592),please verify. NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 2 of 3 T Ad 4,, CITY OF COLLEGE STATION 44441441401041*.t�, Planning o'Development Services daddd�x .,. 9. It appears the existing drainage swell located along the eastern property line will be modified with the development of these tracts, these drainage improvements will need to take into account the 100-yr pathway and verify that the existing adjacent lots will not be negatively impacted. 10. All proposed utility easement widths are subject to change due to design constraints. 11. Please provide a note that addressed the conditions of development permit (#04-62) for the median cut on SH 40 (William D. Fitch) previously Greens Prairie Road. These conditions were more specifically explained in October 28,2004 letters addressed to Jeff Johnston from Alan Gibbs. 12. FYI:At final plat/construction document stage the proposed alignment of Lakeway Drive would need to be adjusted as the north east portion of the proposed alignment is encumbered by a 30-ft Pipeline Easement,or the Pipeline Company must give the first right of refusal to the City of College Station. 13. Note:Although some of the lots within this subdivision that are not adjacent to Lakeway Drive may final plat prior to the construction of Lakeway Drive,in regards to traffic,Lakeway Drive is viewed as serving the 50.547 acres as a whole. Reviewed by: Josh Norton Date:July 23,2007 SANITATION 1. Sanitation is ok with this project. Reviewed by: Wally Urrutia Date: July 18,2007 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans. Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. Page 3 of 3 STAFF REVIEW COMMENTS NO. 1 Project: SPRING CREEK COMMONS (PP) — 07-00500174 PLANNING 1. The boundaries of the plat do not close. Please revise. Discussion — Sven emailed us that this is ok. 2. Corridor Overlay district (OV) also exists on portions of the plat. Please label accordingly. Discussion —This has been labeled. 3. When final plats are submitted, all lots within a phase must be platted. As currently shown, Lots 4, 5, & 6 are all part of Phase 4 and would need to be final platted together. If this is not your intent, please revise the Phase Plan while still ensuring each phase supports the infrastructure required by it. If phase boundaries change in the future, a revised preliminary plat must be submitted. Discussion — Phasing has been revised. 4. Note 5 states that Block 2, Lot 1 is not a buildable lot though the lot appears to require construction of a portion of Lakeway Drive, planting of the 50-foot vegetative buffer and provide underground storm water facilities along the eastern property boundary. This arrangement is not acceptable, please revise. Discussion — General note #5 has been reworded per our discussion to accommodate this concern. 5. The Signage Plan may also be considered for revision. Discussion —The signage plan has been revised per our discussion. 6. The newly created Lot 2, Block 2 does not meet the minimum dimensions required with a C-1 zoning district. As per the October 11, 2005 Parks Board minutes, it is our understanding that this area is to be donated to the City in connection with the adjacent park. Please revise. Discussion — See general note #5 on the plat. 7. Revise the note for the 30' access easement associated with Block 1, Lot 6 to state that the access easement will continue to Lakeway within Block 1, Lot 5. Discussion — These access notes have been revised to state they will be constructed to Lakeway and location determined at the time of final plat. 8. It appears that the 30' access easement through the center of the plat has been removed. Please revise the plat to provide the easement, perhaps in a similar fashion as the aforementioned easement, but with a note stating that it will intersect Lakeway within Block 1, Lot 4. Discussion — Notes regarding this easement have been added to the plat. Spring Creek Commons Preliminary Plat Page 2 ENGINEERING COMMENTS NO. 1 /�5., 1. keway Drive is illustrated as a Major Collector on the city's thoroughfare plan which requires 80-ft Right-of-Way, please revise. Discussion — We are awaiting Bob Cowell's response to our question regarding vested rights o this issue. Please define PDE, as well as any other acronyms. Tiscussion — These acronyms have been defined in the legend. he proposed storm infrastructure is subject to change as the developments drainage report has not yet been submitted. Discussion — Understood. ....All proposed storm infrastructure which serves multiple lots has the option to be built to public standard and located within a public utility easement or located within a private utility easement. Any proposed Private Storm Infrastructure and corresponding Private Drainage Easements should be identified with ownership and maintenance responsibilities defined. Discussion — All private drainage structures/lines have been removed from the plat and replaced with drainage arrows indicating "approximate routes" of these lines, all easements that will be required for these lines will be determined at site plan and dedicated by separate instruments. (see note #8 on the plat) Please verify that all storm infrastructures have been properly identified as private or public, and the appropriate easement illustrated, and ownership and maintenance responsibilities designated. iscussion — See general note #8 on the plat. .ol It appears that some of the storm infrastructure has not been properly located within an easement and may meander in/out of public/private easements. •. cussion — See comment #4 above general note #8 on the plat. ' .34`0 -ase provide the required 20-ft PUE at the rear of all lots, these easements may be split between adjacent properties. .iscussion — See note #9 on the plat. 8. I r records indicate an existing 25-ft PUE located parallel to the property line i' adjacent to SH 6 (Volume 758, Page 592), please verify. Discussion — See attached easement paperwork. It appears this easement is ‘04 20' PUE. appears the existing drainage swell located along the eastern property line will be modified with the development of these tracts, these drainage improvements will need to take into account the 100-yr pathway and verify that the existing adjacent lots will not be negatively impacted. Discussion — Understood. This will be addressed with the drainage report for � t 1, Block 2. All proposed utility easement widths are subject to change due to design constraints. D iscussion — Understood. �L ' lease provide a note that addressed the conditions of development permit /S (#04-62) for the median cut on SH 40 (William D. Fitch) previously Greens Spring Creek Commons Preliminary Plat Page 3 Prairie Road. These conditions were more specifically explained in October 28, 2004 letters addressed to Jeff Johnston from Alan Gibbs. Discussion —We understand that: 1) The property owner or developer is to provide a joint access easement upon the adjacent existing drive removal. 2) In the future event that the existing adjacent driveway is not removed and a Site Plan in submitted utilizing the propose driveway, it may be a condition of the Site Plan for the property owner or developer to construct a right turn lane from a distance east of the proposed driveway to the SH6 frontage road. 3) The property owner or developer will assure that the future southbound Lakeway Drive intersection with Greens Praire will have a "no right turn on red sign posted." 12.FYI: At final plat/construction document stage the proposed alignment of Lakeway Drive would need to be adjusted as the north east portion of the proposed alignment is encumbered by a 30-ft Pipeline Easement, or the Pipeline Company must give the first right of refusal to the City of College Station. Discussion — We are awaiting an answer from Bob Cowell regarding the vesting of this alignment based upon the previous approval of this same alignment on the current preliminary plat. 13.Note: Although some of the lots within this subdivision that are not adjacent to ),3 Lakeway Drive may final plat prior to the construction of Lakeway Drive, in regards to traffic, Lakeway Drive is viewed as serving the 50.547 acres as a whole. Discussion — Per our discussion we understand that we can disregard this comment. Reviewed by: Josh Norton Date: July 23, 2007 SANITATION 1. Sanitation is ok with this project. Discussion — This item was not discussed. Reviewed by: Wally Urrutia Date: July 18, 2007 Spring Creek Commons Preliminary Plat Page 4 (*ffill11114 CITY OF COLLEGE STATION Plannin d Deve t Services 1101 Texas Avenue,P.O.Box 9960 College Station,Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM August 3,2007 TO: Veronica Morgan,P.E.,Mitchell&Morgan,LLP,via va,mitchellandmorgan.com FROM: Jason Schubert,Staff Planner SUBJECT: SPRING CREEK COMMONS (PP) - Preliminary Plat Staff reviewed the above-mentioned Preliminary Plat as requested. The following page is a list of staff review comments detailing items that need to be addressed. If all comments have been addressed and the following information submitted by Monday, August 6, 2007, 10:00 a.m., your project will be placed on the next available Planning and Zoning Commission meeting scheduled for August 16, 2007, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas Avenue. One (1) 24"x 36" copy of the revised Preliminary Plat; Sixteen (16) 11"x 17" copies of the revised Preliminary Plat. Upon receipt of the required documents for the Planning& Zoning meeting,your project will be considered formally filed with the City of College Station. Please note that if all comments have not been addressed,your project will be pulled from the scheduled Planning & Zoning Commission agenda. Your project may be placed on a future agenda once all the revisions have been made and the appropriate fees paid. Once your item has been scheduled for the P&Z meeting, the agenda and staff report can be accessed at the following web site on Monday the week of the P&Z meeting. http://vvww.cstx.gov/home/index.asp?page=2481. If you have any questions or need additional information,please call me at 979.764.3570. Attachments: Staff review comments cc: Frank Mihalopoulos, Corinth Properties,via frankacorinthprop.com Al Smith,St.Joseph Regional Health Center,via asmith a,mail.st-joseph.org Penny Busch,Hammus Company,via pbusch@hamtnesco.com Case file#07-00500174 Home of Texas A&M University '"STAFF REVIEW COMMENTS NO.11'*"" Project: SPRING CREEK COMMONS (PP) - 07-00500174 PLANNING 1. It is our understanding that the area of Lot 6,Block 1 will be reduced. Please revise the plat accordingly. 2. The question regarding the 80'ROW width for Lakeway Drive has been determined. ROW width is not an element to which a project can vest. Please revise the preliminary plat to show the 80'ROW. 3. Please provide the required 20-ft PUE at the rear of all lots, these easements may be split between adjacent properties. In the event that these easements are not illustrated, you will need to submit a variance request to Section 8-1.2 of the subdivision regulations. 4. It appears that several of the existing easements and utilities that were previously illustrated have been removed. Please illustrate all existing easement and utilities per Section 6-C of the Subdivision Regulations. Please remove Note 2, as it does not comply with the Section 6-C of the Subdivision Regulations. Reviewed by: Jason Schubert Date: August 3,2007 ENGINEERING COMMENTS NO. 2 1. Please provide a note on the preliminary plat that addressed the conditions of development permit(#04- 62) for the median cut on SH 40 (William D. Fitch) previously Greens Prairie Road. These conditions were more specifically explained in the October 28, 2004 letters addressed to Jeff Johnston from Alan Gibbs. These requirements should be stated as they were originally stated in the October 28, 2007 letters. 2. At final plat/construction document stage the proposed alignment of Lakeway Drive will need to be adjusted as the north east portion of the proposed alignment is encumbered by a 30-ft Pipeline Easement, or the Pipeline Company must give the first right of refusal to the City of College Station. Our Legal Department has stated right-of-way dedications that are encumbered by other easements will not be accepted. If not revised, this notice will be added as a staff review comment on the staff report to the Planning and Zoning Commission. 3. FYI: Although some of the lots within this subdivision that are not adjacent to Lakeway Drive may final plat prior to the construction of Lakeway Drive,in regards to traffic,Lakeway Drive is viewed as serving the 50.547 acres as a whole. Although this comment does not require any action at this time,it was not intended to be disregarded. Reviewed by:Josh Norton Date:August 3,2007 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 2 of 2 No MITCHELL/� MM MORGAN August 7, 2007 Jason Schubert, Staff Planner 1101 Texas Avenue PO Box 9960 College Station, Texas 77842 Re: SPRING CREEK COMMONS (PP) —Preliminary Plat Dear Jason, Attached please find: • One (1) 24"x3 copy of the revised Preliminary Plat • Sixteen (16) 11 "x17" copies of the revised Preliminary Plat. PLANNING 1 . QUESTION: It is our understanding that the area of Lot 6, Block 1 will be reduced. Please revise the plat accordingly. ANSWER: This has been modified on the attached preliminary plat and matches the final plat recently submitted. 2. QUESTION: The question regarding the 80' ROW width for Lakeway Drive has been determined. ROW width is not an element to which a project can vest. Please revise the preliminary plat to show the 80' ROW. ANSWER: We have modified the ROW to meet the new 80' ROW width requirement. 3. QUESTION: Please provide the required 20-ft PUE at the rear of all lots, these easements may be split between adjacent properties. In the event that these easements are not illustrated, you will need to submit a variance request to Section 8-1.2 of the subdivision regulations. ANSWER: We have shown these 20' PUE's and have added a note stating these are shown for illustrative purposes only and their exact location will be based upon utility locations designed to serve each lot at the time of final platting. 511 UNIVERSITY DRIVE EAST,SUITE 204• COLLEGE STATION,TX 77840• T. 979.260.6963• F. 979.260.3564 13% CIVIL ENGINEERING • HYDRAULICS • HYDROLOGY • UTILITIES • STREETS • SITE PLANS • SUBDIVISIONS 1�� info@mitchellandmorgan.com • www.mitchellandmorgan.com a 4. QUESTION: It appears that several of the existing easements and utilities that were previously illustrated have been removed. Please illustrate all existing easement and utilities per Section 6-C of the Subdivision Regulations. Please remove Note 2, as it does not comply with the Section 6-C of the Subdivision Regulations. ANSWER: Sorry, one of the text layers which described all easements was inadvertently frozen and therefore it did not plot. We have restored that layer and modified note #2 as requested. ENGINEERING COMMENTS NO. 2 1 . QUESTION: Please provide a note on the preliminary plat that addressed the conditions of development permit (#04-62) for the median cut on SH 40 (William D. Fitch) previously Greens Prairie Road. These conditions were more specifically explained in the October 28, 2004 letters addressed to Jeff Johnston from Alan Gibbs. These requirements should be stated as they were originally stated in the October 28, 2007 letters. ANSWER: A note has been added which refers a developer or potential lot owner to development permit #04-62 for additional information regarding conditions that may affect the lots/development of lots along SH40 at Greens Prairie Road. 2. QUESTION: At final plat/construction document stage the proposed alignment of Lakeway Drive will need to be adjusted as the north east portion of the proposed alignment is encumbered by a 30-ft Pipeline Easement, or the Pipeline Company must give the first right of refusal to the City of College Station. Our Legal Department has stated right- of-way dedications that are encumbered by other easements will not be accepted. If not revised, this notice will be added as a staff review comment on the staff report to the Planning and Zoning Commission. ANSWER: We understand that at the time of final plat if the alignment of Lakeway Drive is not shifted out of the 30' pipeline easement then we will need to obtain a first right of refusal from the pipeline company or have them abandon their easement. 3. QUESTION: FYI: Although some of the lots within this subdivision that are not adjacent to Lakeway Drive may final plat prior to the construction of Lakeway Drive, in regards to traffic, Lakeway Drive is viewed as serving the 50.547 acres as a whole. Although this comment does not require any action at this time, it was not intended to be disregarded. ANSWER: We understand that Lakeway Drive is intended to serve the entire 50.547 acres and all of these properties are responsible for its construction per the phase plan on the preliminary plat. Ple. e let us know if you have any questions. Si .erely, t J fa lif 1 cf------) Veronica J.B. ► l•rga P.i., C.F.M. Managing Partner Cc. File