HomeMy WebLinkAboutLetter of Completion FROM :Texcon General Contractors FAX NO. :9796909797 Feb. 29 2008 09:20AM P1
LETTER OF COMPLETION
CITY OF COLLEGE STATION DATE:FEBRUARY 28,2008
ENGINEERING DIVISION
COLLEGE STATION,TEXAS
RE: CASTLEROCK SUBDIVLSON,PFIASE 1B&1 C
To Whom It May Concern:
The purpose of our letter is to request that the following listed improvements be approved
and accepted as being constructed under City inspection and completed according to plans and
specifications as approved and required by the City of College Station,Texas. This approval and
acceptance by the City is requested In order that we may finalize any subcontracts and to affirm
their warranty on the work. This approval and acceptance by the City of the improvements listed
below does hereby void the letter of guarantee for the listed improvements on the above reference
project.
Theone-year warranty is hereby affirmed and agreed to by TEXCON and by their sub-
contractors as indicated by signatures below.
WORK COMPLETED WARRANTY DATE
Streets February 28,2008
Water Utilities February 28,2008
Sanitary Sewer IJtilities February 28,2008
Drainage Facilities February 28,2008
Sidewalks February 28,2008
OWNER: CONTRACTOR:
GREENS PRAIRIE INVESTORS,LTD. TEXCON
(979)690-7250 (979)690-7711
4490 CASTLF.GATE DRIVE 1707 GRAHAM RO t
COLLEGE STATION,TEXAS 77845 COLLEGE STA TX 77:4
4,
SIGNATURE: ::'N _./di i,�. ._ _ SIGNATURE:
Walisce Phillips-Owner Glenn.(ones,PE-:FM-Projeet Manager
ACCEPTANCE&APPROVAL
CITY RI:PRESPNTATI C
�It
C 1, GINEE
FROM :Texcon General Contractors FAX NO. :9796909797 Feb. 29 2008 09:20AM P1
LETTER OF COMPLETION
CITY OF COLLEGE STATION DATE:FEBRUARY 28,2008
ENGINEERING DIVISION
COLLEGE STATION,TEXAS
RE: CASTLEROCK SUBDIVLSON,PHASE 1 B&IC
To Whom It May Concern:
The purpose of our letter is to request that the following listed improvements be approved
and accepted as being constructed under City Inspection and completed according to plans and
specifications as approved and required by the City of College Station,Texas. This approval and
acceptance by the City is requested in order that we may finalize any subcontracts and to affirm
their warranty on the work. This approval and acceptance by the City of the improvements listed
below does hereby void the letter of guarantee for the listed improvements on the above reference
project.
The one-year warranty is hereby affirmed and agreed to by TEXCON and by their sub-
contractors as indicated by signatures below.
WORK COMPLETED WARRANTY DATE
Streets February 28,2008
Water Utilities February 28,2008
Sanitary Sewer Utilities February 28,2008
Drainage Facilities February 28,2008
Sidewalks February 28,2008
OWNER: CONTRACTOR:
GREENS PRAIRIE INVESTORS,LTD. TEXCON
(979)690-7250 (979)690-7711
4490 CASTLFGATE DRIVE 1707 GRAHAM RO 1
COLLEGE STATION,TEXAS 77845 COLLEGE STA TX 77:4
=;/_7 i
/
SIGNATURE: S �_.. _ ":,:r/SIGNATURE:
Wallace 1'hillips-Owner Glenn Jones,PE-.1'M-Projcst Manager
ACCEPTANCE&APPROVAL :::4-"WV.-4 ,
CITY REPRRRHNTATI C
I/
uadd
C 1;; (ANF?t