MEMORANDUM
November 6, 2007
TO: ML Schehin, Saddle Creek Partners, Ltd. via fax# 979.690.2793
FROM: Crissy Hartl, Staff Planner
SUBJECT: SADDLE CREEK PH 2 (FP) - Final Plat
Staff reviewed the above-mentioned final plat as requested. The following page is a list of staff
review comments detailing items that need to be addressed. If all comments have been
addressed and the following information submitted by Monday, November 19, 10:00 a.m., your
project will be placed on the next available Planning and Zoning Commission meeting
scheduled for, December 6, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas Avenue.
One (1) 24"x36" copy of the revised final plat;
Nineteen (19) 11"x17" copies of the revised final plat;
Parkland Dedication in the amount of$ must be submitted prior to the filing of the
final plat;
Easement Dedication Sheet for Temporary Turnaround (delete if not applicable);
One (1) Mylar original of the revised final plat (required after P&Z approval); and
One (1) copy of the digital file of the final plat on diskette or e-mail to
mtrevino@cstx.gov.
Upon receipt of the required documents for the Planning & Zoning meeting, your project will be
considered formally filed with the City of College Station. Please note that if all comments have
not been addressed your project will not be scheduled for a Planning & Zoning Commission
meeting. Your project may be placed on a future agenda once all the revisions have been made
and the appropriate fees paid. Once your item has been scheduled for the P&Z meeting, the
agenda and staff report can be accessed at the following web site on Monday the week of the
P&Z meeting.
http://www.cstx.gov/home/index.asp?page=2481
Please note that a Mylar original of the revised final plat will be required after P&Z approval and
prior to the filing of the plat. If you have any questions or need additional information, please call
me at 979.764.3570.
Attachments: Staff review comments
cc: Joe Schultz, Civil Development, Ltd. via fax# 979.764.7759
Case file#07-00500265
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be
explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans
that have not been pointed out to the City,will constitute a completely new review. 1 of 2
STAFF REVIEW COMMENTS NO. 1
Project: SADDLE CREEK PH 2 (FP) - 07-00500265
PLANNING COMMENTS
1. Staff has noted the difference in the street names between the approved Preliminary Plat
and this Final Plat and contacted Brazos County 911 for their approval of the name
changes.
2. Please provide a 20' PUE along the rear of Lots 34-40, Block 3.
3. Please note that any changes made to the plans, that have not been requested by the City
of College Station, must be explained in your next transmittal letter and "bubbled" on your
plans. Any additional changes on these plans that the City has not been made aware of will
constitute a completely new review.
4. This plat is still under review by the County and BTU. Please contact Gary Arnold and
Randy Trimble for their comments.
Reviewed by: Crissy Hartl Date: November 6, 2007
ENGINEERING COMMENTS NO. 1
1. Please verify that adequate easements have been provided for BTU and Brazos County.
2. Please submit fire flow report.
3. (Construction Docs — Sheet 2) It appears that a gate valve is missing between Sta. 0+00
and 8+00.
Reviewed by: Josh Norton Date: November 5, 2007
GENERAL ELECTRICAL COMMENTS
1. This plat is in the College Station ETJ, but is out of the College Station Utility electric service
area. Customer will have to get with their electric supplier for this area to determine electric
service specifications and requirements.
Reviewed by: Timothy Crabb, CSU Electric, (979) 764-3439 Date: 10/30/07
FIRE COMMENTS
1. No comments.
Reviewed by: Steve Smith Date: 10/31/2007
SANITATION COMMENTS
1. Sanitation is ok with this project.
Reviewed by: Wally Urrutia Date: October 31, 2007
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be
explained in your next transmittal letter and "bubbled"on your plans. Any additional changes on these plans
that have not been pointed out to the City,will constitute a completely new review. 2 of 2