HomeMy WebLinkAboutEngineer's Estimate ., ENGINEERING ESTIMATE OF CONSTRUCTION COST
Lakeside Village Subdivsion-Extension of Eagle Avenue
College Station, Texas
14th December 2006
I j
Item _ Estimated Desc I Estimated Unit Extended
No. Description Quantity of Unit Price I Cost
Sitework and Paving
1 Mobilization/Layout _ _ 1 LSI $10,000.00 $10,000.
2 Site Preparation 0.9 AC $1,000.00 $900
3 Silt Fence 60 LF $2.50 $150
4 Construction Exit-Rock 20 , TONS $60.00 $1,200
5 Erosion&Sediment Control-Misc. Items and SWPPP 1 LS $2,000.00 $2,000
6 Seeding _ 900 SY $0.25 $225
7 Topsoil Stripping&Replacement(Within ROW) 150 CY $2.00 $300
8 General Site Grading-Excavation or Cut 1 0' CY $0.00 $0
9 ADA Ramp-T-Sidewalk Intersection Ambulatory Ramp 2 EA $450.00 $900
10 ADA Ramp-Mid Radius Ambulatory Ramp 1 EA $675.00 $675
11 Sidewalk-4'wide 5,129 SF $4.50 $23,081
12 Lime Stabilized Subgrade 2,945 SY $4.00 $11,780
13 Base Material-8"depth 2,371 SY $8.50 $20,154
14 Asphalt Paving-2'depth 2,371 SY $10.00 $23,710
15 Concrete Curb and Gutter 1,329 LF $9.50 $12,626
16 6"PCC Apron(at Creekside Circle) 922 SF $6.00 $5,532
17 Temporary Tpye III Barricades 1 LS $3,000.00 $3,0001
I I Subtotal $116,232
Sitework and Paving Notes:
1. Units for general site grading for all phases of the project(Phases I and II)plus Eagle Avenue are in the Phase I proposal.
a-n: z .,r tib ,
18 Stardard 5'Curb Inlets 2 EA 3,500 $7,000
19 18"RCP CL III Pipe-Structural Backfill 45 LF 55 $2,475
20 24"RCP CL III Pipe-Structural Backfill 225 LF 70 $15,750
21 Connection to Existing Stormwater Drainage Inlet 1 LS $3,000.00 $3,000
Subtotal $28,225
Domestic Water Supply
22 NONE-Water Line Along Eagle Avnue Part of Phase I Construction
Subtotal $0
Sanitary Sewer
23 NONE-No Sanitary Sewer Lines Along Eagle Avenue ,
Subtotal
Total Sitework $116,232
�E OF • Total Storm Drainage $28,225)
/* • -' • Total Water $0
•
reImoTotal Sewer $0
• •. a•• Q 44481 � i
• ••k, _+ .4 _ TOTAL CONSTRUCTION $144,457
.
Page 1 of 1
" ' ENGINEERING ESTIMATE OF CONSTRUCTION COST
Lakeside Village Subdivsion-Phase I
College Station,Texas
14th December 2006
1 Item ' Estimated I Desc Estimated Unit Extended
No. Description 1 Quantity of Unit Price Cost
Sitework and Paving
1 Mobilization/Layout 1 LS $20,000.00 $20,0001
2 Traffic Control(Along Longmire and at End of Eagle) I 1 LS $1,500.00 $1,500
3 Site Preparation 6.9 AC $1,000.00 $6,930
4 Silt Fence 1,520 LF $2.50 $3,800
5 Construction Exit-Rock _ 20 TONS $60.00 $1,200
6 Erosion&Sediment Control(Including SWPPP) 1 LS $1,500.00 $1,5001
7 Topsoil Stripping&Replacement(Within ROW and Lake Area) 1,290 CY $5.00 $6,450
8 ROWSeedng andl ncluding Around Lake)Topsoil Replacement in Disturbed Areas Within 2,900 SY $0.25 $7251
9 General Site Grading-Excavation or Cut(Including Lake) 1 4,850 CY I $5.00 $24,250
10 General Site Grading-Fill 1 6,940 CY $8.50 $58,990
11 6"Concrete Aprons 2,466 , SF $6.00 $14,796
12 ADA Ramp-T-Sidewalk Intersection Ambulatory Ramp 4 EA $450.00 $1,800
13 ADA Ramp-Mid Radius Ambulatory Ramp 1 EA $675.00 $675
14 Portland Cement Concrete(PCC)Sidewalk-4'wide 3,237 SF $4.50 $14,567
15 Portland Cement Concrete(PCC)Sidewalk-6'wide 700 SF $4.50 $3,150
16 Hot Mix Asphalt Concrete(HMAC)Paving Surface Course-2" 4,274 SY $10.00 $42,740
17 Crushed Rock Base Course Material-6"depth 4,274 SY $7.50 $32,055
18 Lime Stabilized Subgrade Soils 5,309 SY $4.00 $21,236
19 Concrete Curb and Gutter 2,602 LF $9.50 $24,719
20 Ribbon Curb Around Lake 690 LF $12.00 $8,280
Subtotal $289,363
Sitework and Paving Notes: �
1. General site grading is for all phases of the project(Phases I and II)plus Eagle Avenue.
21 Rein Conc Lake Water Outlet Box Structure(with grate) 1 EA $4,000.00 $4,000
22 24"HDPE Pipe-Structural Backfill From Lake to Longmire 249 LF $70.00 $17,430
23 Connect Lake Drain To Exist. Curb Inlet on Longmire Dr. 1 EA $3,000.00 $3,000
24 Trapezoidal concrete drainage flumes from street to lake 160 SF $7.50 $1,200
I Subtotal $25,630
Domestic Water Supply
Inside Phase I Area
25 8"Water PVC CL200(C909)-Structural Backfill 574 LF $35.00 $20,090
26 8"Water PVC CL200(C909)-Non-Structural Backfill 1 349 LF $30.00 $10,470
27 3"Water PVC CL200(C909)-Structural Backfill 0 LF $25.00 $0
28 3"Water PVC CL200(C909)-Non-Structural Backfill 427 LF $20.00 $8,540
29 8"M.J. Gate Valves 3 EA $900.00 $2,7001
30 3"M.J. Gate Valves 2 EA $600.00 $1,2001
31 90° M.J. DIP Bends 8" 11 2 EA $500.00 $1,000
32 45° M.J. DIP Bends-8" 9 EA $460.00 $4,140
33 22.5°M.J. DIP Bends-8" 1 EA $450.00 $450
34 8"x 8"M.J. DIP Tee 2 EA $550.00 $1,100
35 8"M.J. DIP Plug 1 EA $200.00 $200
36 Fire Hydrant Assembly w/Extension 1 EA $3,000.00 $3,000
37 2"Blow off Assembly(At End of 8"WL On Longmire) 1 EA $1,200.00 $1,200
38 8"x 3"M.J. DIP Reducer 2 EA $450.00 $900
39 45° M.J. DIP Bends-3" 1 2 EA $400.00 $800
40 11.25°M.J. DIP Bends-3" 2 EA $400.00 $800
41 Water Service Lines-1"Single Service-Short 1 EA $450.00 $450
L 42 Water Service Lines-1.5"Double Service-Short 2 EA $1,500.00 $3,000
43 Water Service Lines-1"Single Service-Long 2 EA $650.00 $1,300
44 Water Service Lines-1.5"Double Service-Long 10 EA $1,500.00 $15,000
Subtotal, $76,340
Page 1 of 2
' - ' ENGINEERING ESTIMATE OF CONSTRUCTION COST
Lakeside Village Subdivsion-Phase I
College Station, Texas
14th December 2006
Item Estimated Desc Estimated Unit Extended 1
No. Description Quantity 4of Unit Price Cost _
Eagle Avenue"Main"Line
Remove Existing Plug/BO valve from Exist. 12"WL and Connect 11
45Prop 12"WL to Exist 12"WL 1 EA $1,00000 $1,000
46 12'Water PVC CL200(C909)-Structural Backfill 605 LF $45.00 $27,225
47 Gate Valves(MJ)-12" _ 2 EA $1,000.00 $2,000
48 12"x 8"M.J. DIP Tee Fitting 2 EA $500.00 $1,000
49 22.5° M.J. DIP Bends Fitting-12"(for Curvature of End of WL) 2 EA $450.00 $900
50 4"Blow off Assembly at End of Prop 12"WL 1 EA j $1,200.00 $1,200
Subtotal $33,325
Sanitary Sewer
51 8"SDR 26 C-3034 Pipe-Non-structural Backfill 980 LF $45.00 $44,100
52 8"SDR 26 C-3034 Pipe-Structural Backfill 179 LF $60.00 $10,740
53 8"DIP-ANSI/AWWA C1541/A21.5 Pressure Class 350-Non 427 ! LF $70.00 $29,890
structural Backfill
54 10"SDR 26 C-3034 Pipe-Structural Backfill 85 LF $65.00 $5,525
55 10"SDR 26 C-3034 Pipe-Non-Structural Backfill 828 LF $75.00 $62,100
56 Cleanouts at End of 8"SS Line 4 EA $750.00 $3,000 _
57 Standard Manholes-<8'Depth 4 EA $3,000.00 $12,000
58 Standard Manholes-8'-10'Depth 2 EA $3,500.00 $7,000
59 Install Stnd MH Over Existing 12"SS Line(10'to 12'Depth) 2 EA $1,000.00 $2,000
60 By-pass Pumping for Installation of MH Over Exist. SS Line 2 LS $2,000.00 $4,000
60 4"SS Sewer Single Service Lines-Short 4 EA $450.00 $1,800
61 4"SS Sewer Double Service Lines-Short 11 EA $600.00 $6,600
62 4"SS Sewer Single Service Lines-Long 1 EA $750.00 $750
63 4"SS Sewer Double Service Lines-Long 0 EA $850.00 $0
64 Trench Safety 2,499 LF $1.00 $2,499
65 TV Inspection 2,499 LF $1.50 $3,749
Subtotal $195,753
Total Sitework $289,363
Total Storm Drainage $25,630
Total Waterl $109,665
Total Sewer $195,753
_ TOTAL CONSTRUCTION $544,070
I '
ms�sAA � -9
0 M F CONUN,JR. - %I.ii
fill• •
44481 :• 4�
Page 2 of 2
• ' ENGINEERING ESTIMATE OF CONSTRUCTION COST
Lakeside Village Subdivsion-Phase II
College Station,Texas
14th December 2006
Item Estimated I Desc Estimated Unit Extended j
No. Description Quantity of Unit Price Cost 1
1
Sitework and Paving
1 Mobilization/Layout 1 LS $20,000.00 $20,000
2 Site Preparation 6.0 AC $1,000.00 $5,960
3 Silt Fence 1,250 LF $2.50 $3,125
4 Construction Exit-Rock 20 TONS $60.00 $1,200
5 Erosion&Sediment Control-Misc. Items and SWPPP 1 LS $1,500.00 $1,500
6 Seeding 2,498 SY $0.25 $625
7 Topsoil Stripping&Replacement(Within ROW) 998 CY $400.00 $399,200
8 General Site Fill/Grading 1 0 1 CY $8.50 $0
9 ADA Ramp-T-Sidewalk Intersection Ambulatory Ramp 3 EA $450.00 $1,350
10 ADA Ramp-Mid Radius Ambulatory Ramp 1 EA $675.00 $675
11 Sidewalk-4'wide 2,331 SF $4.50 $10,490
12 Lime Stabilized Subgrade 4,884 SY $4.00 $19,536
13 Base Material-6"depth 3,931 SY $7.50 $29,483
14 Asphalt Paving-2"depth 3,931 SY $10.00 $39,310
15 Concrete Curb and Gutter 2,111 LF $9.50 $20,055
16 6"Concrete Aprons 1,701 SF $6.00 $10,206
Subtotal $562,713
Sitework and Paving Notes:
1. Units for general site grading for all phases of the project(Phases I and II)plus Eagle Avenue are in the Phase I work.
I
Recess- ed 5'Curb Inlet w/5'Extention _ u -, >. .2 EA $3,500.0
' 0 $
17 Rece7,000
18 24"HDPE-Structural Backfill I 102 LF $60.00 $6,120
19 24"HDPE-Non-structural Backfill 418 LF $52.00 $21,736
20 Rein. Conc. Discharge Headwall Structure 1 EA $5,000.00 $5,000
21 Rip-rap Erosion Protection at End of Discharge Headwall Str. 1 2 TONS ! $60.00 $90
Subtotal $39,946
Storm Drainage Notes: _ I
1. Grading for the rip-rap and to assure flow away from the headwall structure should be included in the cost for the rip-rap.
1 -
I
Domestic Water Supply 1
23 6"Water PVC CL200(C909)-Structural Backfill 54 LF $35.00 $1,890
24 6"Water PVC CL200(C909)-Non-Structural Backfill 313 LF $30.00 $9,390!
25 3"Water PVC CL200(C909)-Structural Backfill 135 LF $23.00 $3,105
26 3"water PVC CL200(C909)-Non-Structural Backfill 550 LF $18.00 $9,900
27 Gate Valves-6" 3 EA $900.00 $2,700
28 22.5° M.J. DIP Bends-6" 3 EA , $450.00 $1,350
28 6"x 3"M.J. DIP Reducer1 EA $500.00 $500
29 45° M.J. DIP Bends-3" j 6 EA $460.00 $2,760
30 3"x 3"M.J. DIP Tee 1 EA $550.00 $550
31 Fire Hydrant Assembly w/Extension 1 , EA $3,000.00 $3,000
32 Water Service Lines-1"Single Service-Short 1 EA $450.00 $450
33 _Water Service Lines-1"Single Service-Long 2 EA $650.00_ $1,300
34 Water Service Lines-1.5"Double Service-Short 7 EA $1,500.00 $10,500
35 Water Service Lines-1.5"Double Service-Long 6 EA $1,500.00 $9,000
Subtotal $56,395
Page 1 of 2
ENGINEERING ESTIMATE OF CONSTRUCTION COST
Lakeside Village Subdivsion-Phase II
College Station, Texas
14th December 2006
Item Estimated Desc Estimated Unit Extended
No. Description -i Quantity of Unit Price Cost
Sanitary Sewer
36 8"SDR 26 C-3034 Pipe-Non-Structural Backfill 693 LF $45.00 $31,185_
37 8"SDR 26 C-3034 Pipe-Structural Backfill 82 LF $60.00 $4,920
38 Cleanouts at End of 6"SS Line 2 EA $750.00 $1,500
39 Standard Manholes-<8'Depth 3 EA $3,000.00 $9,000
40 4"SS Sewer Single Service Lines-Short I 4 EA $450.00 $1,800
41 4"SS Sewer Double Service Lines-Short 12 EA $600.00 $7,200
42 4"SS Sewer Single Service Lines-Long 0 EA $750.00 $0
43 4"SS Sewer Double Service Lines-Long 0 EA $850.00 _ $0
44 Trench Safety 775 LF $1.00 $775
45 TV Inspection 775 LF $1.50 $1,163
Subtotal $57,543
Total Sitework $562,713
Total Storm Drainage $39,946
Total Water $39,946
Total Sewer $57,543
TOTAL CONSTRUCTION $700,1481