HomeMy WebLinkAboutStaff Report STAFF REPORT
Project Manager: Jennifer Reeves, Staff Planner Report Date: September 22, 2006
Email: jreeves@cstx.gov Meeting Date: October 5, 2006
Project Number: 06-00500186
Item: Presentation, possible action, and discussion on a Vacating Plat of Lot 8R Block
Two and a Final Plat of Lots 8-R & 9 of Block Two of the Edelweiss Business Center
consisting 1.57 acres located at 12815 FM 2154 on the east side of Wellborn Road
between Rock Prairie Road and Mortier Drive. (JR-06-00500186)
Applicant: Jeff McDowell, Agent for Southwood West
i P,fj Staff Recommendations: Staff recommends approval of the Final Plat as submitted.
tY
Item Summary: This item is for the consideration of a Vacating Plat of Lot 8R, Block
o and a Final Plat of Lots 8-R & 9, Block Two of the Edelweiss Business Center. Lot
BR;is being subdivided into Lots 8R & 9. Access to these lots will be provided by exiting
private access easements.
Comprehensive Plan Considerations: The Land Use Plan shows this area as
Regional Retail andris currently zoned C-1 General Commercial. The property fronts on
�YNellborn Road (FM 2154) which is designated a major arterial on the City's
Thoroughfare Plan.
The property is zoned G 1, Ceneral Commercial, and is in compliance with the Unified
Development Ordinance and Subdivision Regulations.
In accordance with the rezoning, a 25-foot landscape buffer is shown along the back of
Lot 9, the common boundary with Edelweiss Estates, a residential subdivision. The
Final Plat is in compliance with the Land Use Plan, which shows the property as Retail
Regional. An 85' private access easement is located along the front of the property.
Access from Wellborn Road was limited to every other lot by the Preliminary Plat.
Budgetary & Financial Summary: This property is located in Sanitary Sewer Impact
Fee Area 92-01. Impact Fees will be due at time of building permit. Current fees for this
area are $232.04 per living unit equivalent (LUE).
Item Background: The Preliminary Plat was approved on 1997. The Final Plat was
approved in 2003, and a subsequent Amending Pat was approved in 2004.
Commission Action Options: The Commission has final authority over the final plat.
The options regarding the final plat are:
• Approval
• Denial
Supporting Materials:
1. Small Area Map (SAM) and Aerial Map
2. Application
3. Copy of Final Plat (provided in packet)
Alete � 7gso-