Loading...
HomeMy WebLinkAboutStaff Comments STAFF REVIEW COMMENTS Project:BIRD POND ESTATES (REZ) -06-00500181 PLANNING 1. As previously discussed in a the facilitation meeting on September 6th and in the round of Staff Review Comments, the flood plain and streams will need to be surveyed and a metes and bounds will be required for these areas. Please provide this information. 2. Please identify all property lines that are associated with this rezoning. 3. Please submit a separate metes and bounds description. This is required with the application and one was submitted with the original, however it did not have closure. With each resubmitted a new metes and bounds description is required if it does not close. Our GIS staff requires this information to check for closure and then it is used for our legal adds and notification letters. 4. Please bold the rezoning boundaries to more easily identify the bounds of the rezone request. 5. (FYI) Please be aware that a new application is not required with each submittal. 6.Would it be at all possible for the subject property for the rezoning to fit on one sheet? Reviewed by: Jennifer Reeves Date: September 11, 2006 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 2 of 2 STAFF REVIEW COMMENTS Project:BIRD POND ESTATES (REZ) - 06-00500181 PLANNING 1. Please delineate the flood plains and streams. 2. Please show flood plain and streams remaining as A-O Agricultural Open. Staff will not be supporting flood plain and streams to be rezoned from A-O to A-OR. 3. Please identify each individual property with the appropriate legal description on the map. 4. Please provide the written legal description of the subject property (metes & bounds of the subdivision) on the map. 5. Please identify the current zoning of all abutting parcels on the map. Reviewed by:Jennifer Reeves Date:August 24,2006 MISCELLANEOUS 1. Irrigation system must be protected by either a Pressure Vacuum Breaker or Reduced Pressure Principle Back Flow Device and installed as per City Ordinance 2394. 2. All Back Flow devises must be installed and tested upon installation as per City Ordinance 2394. ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION GENERAL ELECTRICAL COMMENTS 1. No Comments 2. Outside our service territory. 3. To discuss any of the above electrical comments,please contact Tony Michalsky at 979.764.3438 . Reviewed by:Tony Michalsky Date: 8-23-06