HomeMy WebLinkAboutStaff Report STAFF REPORT
Project Manager: Lindsay Boyer, Staff Planner Report Date: August 25, 2006
Email: lboyer@cstx.gov Meeting Date: September 7, 2006
Project Number: 06-00500170
Item: Presentation, possible action, and discussion on a revised Preliminary Plat for
Lakeside Village Subdivision consisting of 56 lots on 13.79 acres generally located
along the proposed extension of Eagle Avenue and west of Longmire Drive.
Applicant: Ron Lagrone/ Lagrone Construction Co. — Property Owner
Staff Recommendations: Staff recommends approval of the revised Preliminary Plat.
Item Summary: This item is for consideration of an amendment to the Preliminary Plat
for Lakeside Village Subdivision to allow for the phasing of the development and the
development of the lots for lot line construction. This amendment would create two
phases of the development, which would be separated by Eagle Avenue. The plat
remains identical in lot configuration. This plat received a variance at the April 6th
meeting of the Commission to block length and lot configuration. The plat came back to
the Commission on April 20th for reconsideration of the plat which provided pedestrian
access ways per the Commission's recommendation, and changed some lot
configurations that did not receive variances. This plat is identical to the plat that was
approved on April 20th except for the phasing line and the addition of maintenance
easements for lot line construction.
Lot line construction allows the developer to offset the buildings to one side of the lot,
up to the lot line, but requires that a 7.5-foot maintenance easement be provided
between buildings.
Comprehensive Plan Considerations: The Comprehensive Land Use Plan identifies
this area for Single-family Residential Medium Density. A short segment of Eagle
Avenue will be extended through the development of this parcel. Longmire Drive is a
Major Collector and runs north-south connecting Barron Road to FM 2818. Eagle
Avenue is a Minor Collector and connects the SH 6 Frontage Road to the SH 40
Frontage Road. The southwest corner of the parcel is adjacent to a Lick Creek
tributary.
Item Background: This tract was annexed in 1983 and was zoned R-1 Single-family
Residential in November 2005. The tract has not been previously platted. Dove
Crossing Subdivision is developing to the northeast, and existing single-family
subdivisions are to the south.
Budgetary & Financial Summary: OP for the 12-inch water line along Eagle Avenue
will be requested.
Related Advisory Board Recommendations:
The Subdivision Regulations were amended December 15, 2005, to authorize
the City Manager or his designee to accept the Fee for dedications of less than
three (3) acres where:
• There is a sufficient amount of parkland existing in the park zone of the
proposed development; or
• The proposed dedication is insufficient for a Neighborhood Park site under
existing park design standards.
This plat has met these requirements and the City has accepted fee in lieu of
land dedication for this subdivision. This action does not require approval by the
Planning and Zoning Commission.
Commission Action Options: The Commission has final authority over the preliminary
plat. The options regarding the preliminary plat are:
• Approval
• Denial
INFRASTRUCTURE AND FACILITIES
Water: There is a 12-in waterline along Eagle Avenue that will be extended with this
development. The new system for this area is required to meet B/CS Unified Water
and Sewer Design Guidelines for domestic and fire flows. A Water Design Report
for the subdivision is required at the time of Final Plat to ensure compliance.
Water Service: Water to be provided to each lot, as required.
Sewer: There is an existing 18-inch sewer line along the southwest property line
that will be extended with this development. A Sewer Report for the subdivision is
required at the time of Final Plat to insure capacity and compliance with the BCS
Unified Water and Sewer Design Guidelines.
Sewer Service: Sewer to be provided to each lot, as required.
Streets: The Developer is providing access to all lots with conventional-width
streets. Lakeview Drive will be gated and private. Eagle Avenue is a minor
collector and on the City's Thoroughfare Plan and will be extended with this
subdivision. Longmire Drive is an existing major collector on the Plan. An
additional 5 feet of ROW for Longmire Drive will be dedicated with this
development.
Off-site Easements: N/A
Drainage: This development is required to meet the Drainage Ordinance.
Detention is planned for a portion of the development by means of a retention pond
in the gated area of the subdivision. Direct discharge is planned for the remaining
area.
Flood Plain: N/A
Oversize request: OP for the 12-inch water line along Eagle Avenue will be
requested.
Impact Fees: N/A
Parkland Dedication Fees: Based on 56 lots, the Fee-in-lieu of Land will be
$11,088. The Park Development Fee will be $20,048.
Supporting Materials:
1. Small Area Map (SAM) and Aerial Map
2. Application
3. Copy of Preliminary Plat (provided in packet)
STAFF REPORT
Project Manager: Lindsay Boyer, Staff Planner Report Date: August 25, 2006
Email: lboyer@cstx.gov Meeting Date: September 7, 2006
Project Number: 06-00500170
Item: Presentation, possible action, and discussion on a revised Preliminary Plat for Lakeside
Village Subdivision consisting of 56 lots on 13.79 acres generally located along the proposed
extension of Eagle Avenue and west of Longmire Drive,
Applicant: Ron Lagrone / Lagrone Construction Co. — Property Owner
Staff Recommendations: Staff recommends approval of the revised Preliminary Plat.
Item Summary: This item is for consideration of an amendment to the Preliminary Plat for
Lakeside Village Subdivision to allow for the phasing of the development and the development
of the lots for lot line construction. This amendment would create two phases of the
development, which would be separated by Eagle Avenue. The plat remains identical in lot
configuration. This plat received a variance at the April 6th meeting of the Commission to block
length and lot configuration. The plat came back to the Commission on April 20th for
reconsideration of the plat which provided pedestrian access ways per the Commission's
recommendation, and changed some lot configurations that did not receive variances. This plat
is identical to the plat that was approved on April 20th except for the phasing line and the
addition of maintenance easements for lot line construction.
Lot line construction allows the developer to offset the buildings to one side of the lot, up to the
lot line, but requires that a 7.5-foot maintenance easement be provided between buildings.
Comprehensive Plan Considerations: The Comprehensive Land Use Plan identifies this area
for Single-family Residential Medium Density. A short segment of Eagle Avenue will be
extended through the development of this parcel. Longmire Drive is a Major Collector and runs
north-south connecting Barron Road to FM 2818. Eagle Avenue is a Minor Collector and
connects the SH 6 Frontage Road to the SH 40 Frontage Road. The southwest corner of the
parcel is adjacent to a Lick Creek tributary.
Item Background: This tract was annexed in 1983 and was zoned R-1 Single-family
Residential in November 2005. The tract has not been previously platted. Dove Crossing
Subdivision is developing to the northeast, and existing single-family subdivisions are to the
south.
Budgetary & Financial Summary: OP for the 12-inch water line along Eagle Avenue will be
requested.
Related Advisory Board Recommendations:
The Subdivision Regulations were amended December 15, 2005, to authorize the City
Manager or his designee to accept the Fee for dedications of less than three (3) acres
where:
• There is a sufficient amount of parkland existing in the park zone of the proposed
development; or
• The proposed dedication is insufficient for a Neighborhood Park site under existing park
design standards.
This plat has met these requirements and the City has accepted fee in lieu of land
dedication for this subdivision. This action does not require approval by the Planning and
Zoning Commission.
Commission Action Options: The Commission has final authority over the preliminary plat.
The options regarding the preliminary plat are:
■ Approval
■ Denial
INFRASTRUCTURE AND FACILITIES
Water: There is a 12-in waterline along Eagle Avenue that will be extended with this
development. The new system for this area is required to meet B/CS Unified Water and
Sewer Design Guidelines for domestic and fire flows. A Water Design Report for the
subdivision is required at the time of Final Plat to ensure compliance.
Water Service: Water to be provided to each lot, as required.
Sewer: There is an existing 18-inch sewer line along the southwest property line that will be
extended with this development. A Sewer Report for the subdivision is required at the time
of Final Plat to insure capacity and compliance with the BCS Unified Water and Sewer
Design Guidelines.
Sewer Service: Sewer to be provided to each lot, as required.
Streets: The Developer is providing access to all lots with conventional-width streets.
Lakeview Drive will be gated and private. Eagle Avenue is a minor collector and on the
City's Thoroughfare Plan and will be extended with this subdivision. Longmire Drive is an
existing major collector on the Plan. An additional 5 feet of ROW for Longmire Drive will be
dedicated with this development.
Off-site Easements: N/A
Drainage: This development is required to meet the Drainage Ordinance. Detention is
planned for a portion of the development by means of a retention pond in the gated area of
the subdivision. Direct discharge is planned for the remaining area.
Flood Plain: N/A
Oversize request: OP for the 12-inch water line along Eagle Avenue will be requested.
Impact Fees: N/A
Parkland Dedication Fees: Based on 56 lots, the Fee-in-lieu of Land will be $11,088. The
Park Development Fee will be $20,048.
Supporting Materials:
1. Small Area Map (SAM) and Aerial Map
2. Application
3. Copy of Preliminary Plat (provided in packet)