HomeMy WebLinkAboutStaff Review STAFF REVIEW COMMENTS NO. 1
Project: FRANK VISOSKI (FP-REPLAT) - 06-00500062
PLANNING
1. The construction documents and reports are still under review and may affect the
plat.
2. As discussed in the pre application meeting on January 4, 2006, please provide
cross access easement.
Reviewed by: Jennifer Reeves Date: 04-06-06
ELECTRICAL
Developer installs conduit per city specs and design.
City will provide drawings for conduit installation.
Developer provides 30' of rigid or IMC conduit for riser poles. City installs riser.
Developer to intercept existing conduit at designated transformers and extend as
required.
If conduit does not exist at designated transformer, developer to furnish and install
conduit as shown on electrical layout.
Developer pours transformer pad(s) per city specs and design.
Developer installs pull boxes & secondary pedestals as per city specs and design.(pull
boxes & secondary pedestals provided by the city).
Developer provides digital AutoCAD 2000 or later version of plat and/or site plan email to
wdavis@cstx.gov
Developer provides load data for project.
Developer provides temporary blanket easement for construction purposes.
Developer provides easements for electric infrastructure as installed for electric lines
(including street lights). 15' Easement to be granted in rear of property along Poplar
Street. 10' Easement to be granted to the south right of way line of University Drive, and
a 10' easement along the south right of way line along the north property line of Lot 18R.
To discuss any of the above electrical comments, please contact Weldon Davis at
979.764.5027.
Reviewed by: Weldon Davis Date: April 4, 2006
1. If No Additional Access is Required, No Comment. However, if the entire property is
redeveloped only one (1) access drive will be permitted per TxDOT access spacing rules
for 40 MPH. Additional access will be to Poplar Street. Appropriate permits will be
required for any future work in the ROW @ this site, which should include drainage,
etc.
Reviewed by: Karl Nelson, TXDOT Date: 04-07-06
NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained
in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not
been pointed out to the City,will constitute a completely new review. 2