HomeMy WebLinkAboutStaff Review STAFF REVIEW COMMENTS NO. 1
Project: ROCK PRAIRIE BAPTIST CHURCH (FP) - 06-00500024
PLANNING
1. Provide access easement prior to resubmitting the preliminary and final plats so that
the separate instrument may be reflected on the plats.
2. The application is not signed.
3. Amend 'not plated' to 'not platted'.
4. FYI: The current design for Rock Prairie Road is a minor arterial, bike lane option, in
accordance with the City's current thoroughfare and bicycle facility plans. This will
provide a raised median with both openings and turn pockets, 2 through lanes each
way, as well as a striped bike lane each way. Six foot wide sidewalks are also
planned to meander slightly within the right of way and utility easements.
5. Emphasize subdivision boundary with heavier line weights.
6. Show "Owner(s)" at the bottom of the last line for the Certificate of Ownership and
Dedication.
7. Label the certifications the appropriate labels as indicated in Chapter 9 Appendix of
the Subdivision Regulations.
8. Label the surrounding parcels with ownership, volume/page, plat status.
9. Any, all applicable changes to the plats must also be reflected on the site plan for the
church accordingly.
10. The construction documents and reports are still under review and may affect the
plat.
Reviewed by: Trey Fletcher Date: March 8, 2006
ENGINEERING
1. Please verify metes and bounds are correct so that the plat closes.
2. The proposed 35-ft Drainage/PUE is appropriate as illustrated.
3. Please change the 15-ft PUE along Rock Prairie Rd. to a 30-ft PUE. Once the
ROW acquisition is complete for the additional 10-ft of ROW there will be a 20-ft
PUE left for public utilities.
Reviewed by: Josh Norton Date: March 8, 2006
NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained
in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not
been pointed out to the City,will constitute a completely new review. 2