HomeMy WebLinkAboutStaff Comments CITY OF COIT FGE STATION
Planning d.Development Services
1101 Texas Avenue, P.O. Box 9960
College Station, Texas 77842
Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
January 7, 2008
TO: Natalie Ruiz, IPS Group via email
FROM: Matt Robinson, Staff Planner
SUBJECT: 1910 TEXAS AVE (PDD) — Rezoning
Staff reviewed the above-mentioned rezoning as requested. The following page is a list of staff
review comments detailing items that need to be addressed. Please address all comments and
submit the following information by Monday, January 14th, 10:00 a.m., for your project to be
placed on the next available Planning & Zoning Commission (P&Z) meeting scheduled for
February 7th, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas Avenue:
One (1) 24"x36" copy of the revised Rezoning Map;
Nineteen (19) 11"x17" copies of the revised Rezoning Map;
Please note that if all comments have not been addressed, your project will be not be scheduled
for the P&Z agenda. Your project may be placed on a future agenda once all comments have
been addressed and the appropriate re-advertising fees paid.
Once your item has been scheduled for the P&Z meeting, the agenda and staff report can be
accessed at the following web site on Monday the week of the P&Z meeting.
http://www.cstx.gov/home/index.asp?page=2481
If you have any questions or need additional information, please call me at 979.764.3570.
Attachments: Staff Review Comments
pc: Kathy Strimple, HEB Grocery Company, LP, via US Mail
Case file #07-00500339
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be
explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans
that have not been pointed out to the City, will constitute a completely new review. 1 of 2
STAFF REVIEW COMMENTS NO. 1
Project: 1910 TEXAS AVE (PDD) — (07-00500339)
PLANNING
1. On application the listed acreage is 0.754 acres, whereas the concept plan lists the area as
0.778 acres. Please correct.
Reviewed by: Matt Robinson Date: January 7, 2008
ELECTRICAL COMMENTS REQUIRING IMMEDIATE ATTENTION
1. Developer provides temporary blanket easement for construction purposes.
2. Developer provides easements for electric infrastructure as installed for electric lines
3. Transformer lead time is approximately 42 weeks. Electrical load information needs to be
submitted as soon as it is available to avoid construction delays.
GENERAL ELECTRICAL COMMENTS
1. Developer installs conduit per City specs and design.
2. City will provide drawings for conduit installation.
3. Developer provides 30' of rigid or IMC conduit for riser poles. City installs riser.
4. Developer to intercept existing conduit at designated transformers and extend as required.
5. If conduit does not exist at designated transformer, developer to furnish and install conduit
as shown on electrical layout.
6. Developer pours transformer pad(s) per City specs and design.
7. Developer installs pull boxes and secondary pedestals as per City specs and design (pull
boxes and secondary pedestals provided by the City).
8. Developer provides digital AutoCAD 2000 or later version of plat and/or site plan.
Email to: sweido@cstx.gov.
9. Developer provides load data for project.
10. To discuss any of the above electrical comments please contact Sam Weido at
979.764.6314.
Reviewed by: Sam Weido Date: 1-3-08
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be
explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans
that have not been pointed out to the City, will constitute a completely new review. 2 of 2